Manor Royal Highways Improvements, Crawley

Share Manor Royal Highways Improvements, Crawley on Facebook Share Manor Royal Highways Improvements, Crawley on Twitter Share Manor Royal Highways Improvements, Crawley on Linkedin Email Manor Royal Highways Improvements, Crawley link

Project Overview

This third and final phase has begun in February 2025 to improve the extension of the eastbound bus lane which will provide a dedicated bus route that connects the A23 London Road with Gatwick Road. This phase of works is expected to be completed in September 2025.

The bus lane extension is part of the County Council’s Bus Service Improvement Plan, which is funded by a grant from the Department for Transport. It is designed to enhance the reliability of local bus services and reduce passengers’ journey times. The works will also aim to improve infrastructure durability and reduce maintenance cost over several years.


From the back (closest to the bus) from left to right – Cllr Michael Jones (CBC), Cllr Paul Marshall (WSCC) and Nick Hill (Metrobus). Second row from left to right – Steve Sawyer (Manor Royal BID), Cllr Atif Nawaz (CBC), Nick Burrell (WSCC), Gill Foster (WSP), Cllr Bob Lanzer (WSCC), Dipo Lafinhan (WSCC), Dave Jackson (Landbuild).

West Sussex County Council entered into an Enhanced Partnership with local bus operators in March 2024 to deliver countywide bus service patronage recovery and improvements in line with the Bus Back Better National Bus Strategy for England. Following an ambitious Bus Service Improvement Plan (BSIP) submitted in October 2021, the Department for Transport (DfT) confirmed that the council had been granted £12m towards capital projects from a total £17.4m award over three years. £2.67m of this £12m is funding this strategically important final phase of bus lane infrastructure aligned to the Crawley Growth Programme objectives of implementing improvements across the town to support business investment and employment growth.

Manor Royal Phase 3 Overview Plan


Manor Royal Phase 3 Overview Drawing


Project Updates

Updated 17/04/2025

WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

Week 10 Summary

This week, the contractors have been focused mainly within section 3 and around the 4 way lights and Thales gate 2. Temporary lights have been put in place and are running well. 2 traffic islands have been removed as part of the permanent works. Excavations to the failed carriageway have been carried out and the placement of subbase has been moving forward. Openreach have been on site to slew, lower and install more infrastructure.


Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.

Look Ahead – Week 11 (Section 3)

  • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Temporary lights will remain in place.
  • Bus lane Construction: Type1 being placed and new kerb installation starts.
  • Section 2: Enabling works up to the bus stop will start.
  • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.


Press Releases

For recent press releases, please click on the links below (opens in a new tab):

Bus lane to be extended as part of the Manor Royal highway improvement scheme


Alternate formats

If you require any of the information for this project in an alternative format, please contact us on 01243 777100 or email us at ManorRoyal@westsussex.gov.uk. If you are deaf or hard of hearing and have an NGT texting app installed on your computer, laptop or smartphone, you can contact us on 18001 01243 777100.

Survey web browser compatibility

Please use one of the browsers below when completing the survey to ensure it looks and works as it should. These are:

· Microsoft Edge version 86 and above

· Chrome version 86 and above

· Firefox version 78 and above

· Safari version 14 and above

Project Overview

This third and final phase has begun in February 2025 to improve the extension of the eastbound bus lane which will provide a dedicated bus route that connects the A23 London Road with Gatwick Road. This phase of works is expected to be completed in September 2025.

The bus lane extension is part of the County Council’s Bus Service Improvement Plan, which is funded by a grant from the Department for Transport. It is designed to enhance the reliability of local bus services and reduce passengers’ journey times. The works will also aim to improve infrastructure durability and reduce maintenance cost over several years.


From the back (closest to the bus) from left to right – Cllr Michael Jones (CBC), Cllr Paul Marshall (WSCC) and Nick Hill (Metrobus). Second row from left to right – Steve Sawyer (Manor Royal BID), Cllr Atif Nawaz (CBC), Nick Burrell (WSCC), Gill Foster (WSP), Cllr Bob Lanzer (WSCC), Dipo Lafinhan (WSCC), Dave Jackson (Landbuild).

West Sussex County Council entered into an Enhanced Partnership with local bus operators in March 2024 to deliver countywide bus service patronage recovery and improvements in line with the Bus Back Better National Bus Strategy for England. Following an ambitious Bus Service Improvement Plan (BSIP) submitted in October 2021, the Department for Transport (DfT) confirmed that the council had been granted £12m towards capital projects from a total £17.4m award over three years. £2.67m of this £12m is funding this strategically important final phase of bus lane infrastructure aligned to the Crawley Growth Programme objectives of implementing improvements across the town to support business investment and employment growth.

Manor Royal Phase 3 Overview Plan


Manor Royal Phase 3 Overview Drawing


Project Updates

Updated 17/04/2025

WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

Week 10 Summary

This week, the contractors have been focused mainly within section 3 and around the 4 way lights and Thales gate 2. Temporary lights have been put in place and are running well. 2 traffic islands have been removed as part of the permanent works. Excavations to the failed carriageway have been carried out and the placement of subbase has been moving forward. Openreach have been on site to slew, lower and install more infrastructure.


Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.

Look Ahead – Week 11 (Section 3)

  • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Temporary lights will remain in place.
  • Bus lane Construction: Type1 being placed and new kerb installation starts.
  • Section 2: Enabling works up to the bus stop will start.
  • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.


Press Releases

For recent press releases, please click on the links below (opens in a new tab):

Bus lane to be extended as part of the Manor Royal highway improvement scheme


Alternate formats

If you require any of the information for this project in an alternative format, please contact us on 01243 777100 or email us at ManorRoyal@westsussex.gov.uk. If you are deaf or hard of hearing and have an NGT texting app installed on your computer, laptop or smartphone, you can contact us on 18001 01243 777100.

Survey web browser compatibility

Please use one of the browsers below when completing the survey to ensure it looks and works as it should. These are:

· Microsoft Edge version 86 and above

· Chrome version 86 and above

· Firefox version 78 and above

· Safari version 14 and above

  • Week 10 Update

    Share Week 10 Update on Facebook Share Week 10 Update on Twitter Share Week 10 Update on Linkedin Email Week 10 Update link

    Week 10 Summary

    This week, the contractors have been focused mainly within section 3 and around the 4 way lights and Thales gate 2. Temporary lights have been put in place and are running well. 2 traffic islands have been removed as part of the permanent works. Excavations to the failed carriageway have been carried out and the placement of subbase has been moving forward. Openreach have been on site to slew, lower and install more infrastructure.

    Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.Traffic islands have been removed as part of the permanent works on Manor Royal, Crawley.

    Look Ahead – Week 11 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Temporary lights will remain in place.
    • Bus lane Construction: Type1 being placed and new kerb installation starts.
    • Section 2: Enabling works up to the bus stop will start.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 9 Update

    Share Week 9 Update on Facebook Share Week 9 Update on Twitter Share Week 9 Update on Linkedin Email Week 9 Update link

    Updated 11/04/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 9 Summary

    This week, the contractors have been focused mainly within section 3. Excavations for the bus lane have continued and further accommodating works for utility works have been carried out. The contractors are currently in the process of starting the construction phase. All road markings around the 4 way lights at Thales gate 2 to Crompton way have been removed.

    Bus lane excavation continues to accommodate utility works in Manor Royal, CrawleyBus lane excavation continues to accommodate utility works on Manor Royal, Crawley

    Look Ahead – Week 10 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Temporary lights will be in place from Monday to allow the decommissioning of the 4 ways and allow the removal of the 2 centre islands.
    • Bus Lane Excavation: Small sections of excavation will continue.
    • Bus lane Construction: Type1 to be installed and setting up for new kerbs.
    • Thales gate 2: 4 way lights decommissioned and removal of traffic islands
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 8 Update

    Share Week 8 Update on Facebook Share Week 8 Update on Twitter Share Week 8 Update on Linkedin Email Week 8 Update link

    Updated 07/04/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 8 Summary

    This week, Landbuild has been focused mainly within section 3. Excavations for the bus lane have continued and the new drainage gullies are being installed. VM have been on site to lower their asset across the maintenance bay and Enervio have been on site removing lighting columns and starting the installation of new.

    Installation of drainage gullies in Manor Royal, Crawley

    Look Ahead – Week 9 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Adaptions to the 4 way lights at the junction on Crompton way to facilitate the removal of the traffic islands.
    • Bus Lane Excavation: Earthworks and drainage will continue for the new bus lane within Section 3.
    • Bus lane Construction: Type1 to be installed and preparing for the new kerb lines.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 7 Update

    Share Week 7 Update on Facebook Share Week 7 Update on Twitter Share Week 7 Update on Linkedin Email Week 7 Update link

    Updated 28/03/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 7 Summary

    The Gas main diversion has been completed successfully and works have been progressing with the widening for the new bus lane. Works have included,

    • Removal of the old gas main.
    • Accommodation works for other utility providers.
    • Preparing the formation in readiness for the construction build up.
    Gas main route diversion at Manor Royal, CrawleyGas main route diversion at Manor Royal, Crawley

    Look Ahead – Week 8 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow.
    • Bus Lane Excavation: Earthworks and drainage will continue for the new bus lane within Section 3.
    • Bus lane Construction: Type1 to be installed and preparing for the new kerb lines.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 6 Update

    Share Week 6 Update on Facebook Share Week 6 Update on Twitter Share Week 6 Update on Linkedin Email Week 6 Update link

    Updated 21/03/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 6 Summary

    This week, the contractors have focused on section 3, collaborating with Southern Gas Network (SGN) to dig a trench for the gas main diversion route. Installation of a new pipe line which will be live this week enabling the old line to be removed to facilitate the new bus lane.

    Section 2, will be accommodating works on the 4-way traffic signals to allow Telent to temporarily adapt the current signals to enable island removal. You can find relevant drawings under the photos section on the right side of the webpage.

    Gas main route diversion at Manor Royal, Crawley


    Look Ahead – Week 7 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow.
    • Gas Main Diversion Works: SGN will be commissioning the new main.
    • Bus Lane Excavation: Earthworks and drainage will continue for the new bus lane within Section 3.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 5 Update

    Share Week 5 Update on Facebook Share Week 5 Update on Twitter Share Week 5 Update on Linkedin Email Week 5 Update link

    Project Updates

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 5 Summary

    This week, the contractors have focused on section 3, collaborating with Southern Gas Network (SGN) to dig a trench for the gas main diversion route. You can find relevant drawings under the photos section on the right side of the webpage.

    Gas main route diversion at Manor Royal, Crawley


    Look Ahead – Week 6 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow.
    • Gas Main Diversion Works: SGN will be installing the new main.
    • Bus Lane Excavation: Earthworks will continue for the new bus lane within Section 3.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 4 Update

    Share Week 4 Update on Facebook Share Week 4 Update on Twitter Share Week 4 Update on Linkedin Email Week 4 Update link

    Week 4 Summary

    The contractors' main focus this week has been within section 3 (please see drawings under photos sections on right side of the webpage):

    • Reduced level excavation for the new bus lane.
    • Working with Southern Gas Network (SGN) to dig a trench for the gas main diversion route.
    • Installing Heras fencing around trees within working area to provide tree protection in line with West Sussex tree arboriculturist's guidelines.

    Look Ahead – Week 5 (Section 3)

    • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges.
    • Gas Main Diversion Works: Trenching activities will continue in collaboration with SGN to facilitate the diversion of existing gas infrastructure.
    • Bus Lane Excavation: Earthworks will continue for the new bus lane within Section 3.
    • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 3 Update

    Share Week 3 Update on Facebook Share Week 3 Update on Twitter Share Week 3 Update on Linkedin Email Week 3 Update link

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.

    Week 3 Summary

    The contractors' main focus this week has been within section 3. Reduced level excavation for the new bus lane. Excavating a trench for the gas main diversion route in collaboration with Sothern Gas Network (SGN). Installing Heras fencing around trees within the working area to provide tree protection inline with West Sussex tree arbour culturalist guidelines.

    Look Ahead – Week 4 (Section 3)

    Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges.

    Gas Main Diversion Works: Trenching activities will continue in collaboration with SGN to facilitate the diversion of existing gas infrastructure.

    Bus Lane Excavation: Earthworks will continue for the new bus lane within Section 3.

    Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.

  • Week 2 Update

    Share Week 2 Update on Facebook Share Week 2 Update on Twitter Share Week 2 Update on Linkedin Email Week 2 Update link

    Updated 21/02/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. Currently, construction activities are being carried out with minimal carriageway incursions, ensuring that traffic flow remains unaffected.

    Week 2 Summary

    The contractors' main focus this week has been on carrying out trial hole investigations to pinpoint the exact locations of statutory services. These works are necessary to support upcoming service diversions. Excavation works for the new bus lane are now underway in section 3 alongside the excavation for the new proposed line for the gas main diversion works, enabling the construction of the new bus lane.

    Look Ahead – Week 3 (Section 3)

    • Traffic Management Implementation: A designated running lane will be introduced to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges.
    • Gas Main Diversion Works: Trenching activities will continue in collaboration with SGN to facilitate the diversion of existing gas infrastructure.
    • Bus Lane Excavation: Earthworks will continue for the new bus lane within Section 3.
    • Pedestrian Access: The pedestrian crossing within Section 3 will be closed from Monday; however, alternative crossing points to the East and West will remain fully operational.

    We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.





  • Weekly 1 Update

    Share Weekly 1 Update on Facebook Share Weekly 1 Update on Twitter Share Weekly 1 Update on Linkedin Email Weekly 1 Update link

    Updated 14/02/2025

    WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. Currently, construction activities are being carried out with minimal carriageway incursions, ensuring that traffic flow remains unaffected.

    Week 1 Summary

    Establishing site compounds and trial hole investigations to pinpoint the exact locations of statutory services have been the contractors' main priorities this week. These works are essential to facilitate upcoming service diversions, enabling the construction of the new bus lane.

    Look Ahead – Week 2 (Section 3)

    • Traffic Management Implementation: A designated running lane will be introduced to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges.
    • Gas Main Diversion Works: Trenching activities will commence in collaboration with SGN to facilitate the diversion of existing gas infrastructure.
    • Bus Lane Excavation: Earthworks will begin for the new bus lane within Section 3.

    WSCC remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project.

Page last updated: 17 Apr 2025, 05:16 PM