Week 14 Update
WSCC appreciate your patience and cooperation as work progresses on the Manor Royal project. The bus lane to the southern side of Manor Royal has been suspended to facilitate construction activities which are currently carried out with traffic management in place to utilise the northern lane as a running lane for the machinery and providing a safety zone.
Week 14 Summary
This week, the contractors have been focused mainly within section 2 and 3. Temporary lights remain with some minor layout changes. Traffic signal ducting is currently being installed on the southern side of section 3 whilst in section 2 is being excavate to formation for the new bus lane with drainage works and the placing of type 1. The bus stop within section 2 remains open. However, will be closed from 27 May 2025
Look Ahead – Week 15 (Section 3 and section 2)
- Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges. Bus lane suspension of the bus lane up to Faraday road to simplify traffic flow. Temporary lights will remain in place.
- Section 3 South: Traffic signal ducting continues to be installed.
- Section 2: Excavations to formation levels for the bus lane. Drainage works and the placing of type 1 continue.
- Section 2 Bus Stop: The bus stop will remain open until the 27 May 2025, working on the east and west sides to reduce the duration of impact to anyone using the service. The next closest stop will be at Faraday Road.
- Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.
We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.