Halogen Bulb Replacement Programme
The Project
The three-year planned Halogen Bulb Replacement Programme (HRP) to replace all the West Sussex County Council owned traffic signals from halogen to LED technology draws second year to a close. The programme has successfully converted 70% of the planned sites to LED, completing 63 sites. This includes 5 traffic signal-controlled junctions and 58 standalone crossings. Areas like East Grinstead, Horsham, and Haywards Heath are now fully operating with LED traffic signals.
As we are approaching towards the end of the Programme. Please see sustainable case study attached in the document section to the right along with Puffin crossing leaflet.
Junction refurbishment at Southwater
Why are we doing this work
The project will contribute significantly towards WSCC pledge to become carbon neutral by 2030 -see Climate Change Strategy (opens in new window). The LED traffic signal heads used on this programme have an annual CO2e (Carbon Dioxide Equivalent) reduction per unit of 71kg against the typical halogen equivalent. 331 traffic signal heads have now been replaced, which equates to an annual CO2e reduction made to date of 23,501kg from the traffic signal head replacements alone.
Additionally, this will reduce the need for annual lamp replacements by about 993 lamps. And over the LED's expected lifespan, it will save a total of 9,930 lamp changes. This will bring several benefits, including cost savings, less disruption for road users, and a reduction in carbon and material waste from operating the traffic signals.
What are we doing
Along with the LED upgrades, the program has undertaken extensive refurbishments, replacing all traffic signal equipment and upgrading underground services to reduce future maintenance. Additionally, improvements are being made to the footway areas around crossings, such as updating road markings and clearing vegetation.
At the programme’s inception, 94 sites were planned. However, 4 of those sites were withdrawn due to further planned developer works and upgrades made through WSCC Active Travel projects.
Third Year Programme
Plans and preparations for the third and final year of the HRP are now in progress, focusing on upgrading the remaining sites, which will primarily be located along the coastal regions of the county.
Key areas include 6 sites planned within Chichester, including the junction of Southgate, Chichester, located adjacent to the Bus Station and Train Station. As well as Bognor Regis, Felpham, Littlehampton, Lancing and Worthing. With some final sites left to deliver in Burgess Hill and Crawley. In total, 27 sites will be completed in the 2025/26 financial year, comprised of 3 junctions and 24 signal-controlled crossings.
Design Status for Third Year Programme:

Alternative formats and accessibility
If you require any of this information in an alternative format, then please contact us via email at CCDTrafficSignals@westsussex.gov.uk or by telephone on 01243 777 100 and we will do our best to assist you. If you are deaf or hard of hearing and have an NGT texting app installed on your computer, laptop or smartphone, you can contact us on 18001 01243 777 100.
Please note you can use the Google Translate option in the top right hand corner to specify which language you would like to use to access this page.
For more information about the accessibility of this website, please see our Accessibility tab (opens in new window) at the foot of the page.
The Project
The three-year planned Halogen Bulb Replacement Programme (HRP) to replace all the West Sussex County Council owned traffic signals from halogen to LED technology draws second year to a close. The programme has successfully converted 70% of the planned sites to LED, completing 63 sites. This includes 5 traffic signal-controlled junctions and 58 standalone crossings. Areas like East Grinstead, Horsham, and Haywards Heath are now fully operating with LED traffic signals.
As we are approaching towards the end of the Programme. Please see sustainable case study attached in the document section to the right along with Puffin crossing leaflet.
Junction refurbishment at Southwater
Why are we doing this work
The project will contribute significantly towards WSCC pledge to become carbon neutral by 2030 -see Climate Change Strategy (opens in new window). The LED traffic signal heads used on this programme have an annual CO2e (Carbon Dioxide Equivalent) reduction per unit of 71kg against the typical halogen equivalent. 331 traffic signal heads have now been replaced, which equates to an annual CO2e reduction made to date of 23,501kg from the traffic signal head replacements alone.
Additionally, this will reduce the need for annual lamp replacements by about 993 lamps. And over the LED's expected lifespan, it will save a total of 9,930 lamp changes. This will bring several benefits, including cost savings, less disruption for road users, and a reduction in carbon and material waste from operating the traffic signals.
What are we doing
Along with the LED upgrades, the program has undertaken extensive refurbishments, replacing all traffic signal equipment and upgrading underground services to reduce future maintenance. Additionally, improvements are being made to the footway areas around crossings, such as updating road markings and clearing vegetation.
At the programme’s inception, 94 sites were planned. However, 4 of those sites were withdrawn due to further planned developer works and upgrades made through WSCC Active Travel projects.
Third Year Programme
Plans and preparations for the third and final year of the HRP are now in progress, focusing on upgrading the remaining sites, which will primarily be located along the coastal regions of the county.
Key areas include 6 sites planned within Chichester, including the junction of Southgate, Chichester, located adjacent to the Bus Station and Train Station. As well as Bognor Regis, Felpham, Littlehampton, Lancing and Worthing. With some final sites left to deliver in Burgess Hill and Crawley. In total, 27 sites will be completed in the 2025/26 financial year, comprised of 3 junctions and 24 signal-controlled crossings.
Design Status for Third Year Programme:

Alternative formats and accessibility
If you require any of this information in an alternative format, then please contact us via email at CCDTrafficSignals@westsussex.gov.uk or by telephone on 01243 777 100 and we will do our best to assist you. If you are deaf or hard of hearing and have an NGT texting app installed on your computer, laptop or smartphone, you can contact us on 18001 01243 777 100.
Please note you can use the Google Translate option in the top right hand corner to specify which language you would like to use to access this page.
For more information about the accessibility of this website, please see our Accessibility tab (opens in new window) at the foot of the page.
-
December Update
Share December Update on Facebook Share December Update on Twitter Share December Update on Linkedin Email December Update linkWe have now completed 19 sites, with a further one site is now completed. The Halogen Replacement Programme will now resume in January 2026.
Please see below the November planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Completed
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
Completed
Radford Road near Gatwick Road, Crawley
Crawley
10 November 2025
14 November 2025
Completed
Sea Road near South Terrace, Littlehampton
Arun
24 November 2025
5 December 2025
Completed
We have now completed 19 sites, with a further one site is now completed. The Halogen Replacement Programme will now resume in January 2026.
Please see below the November planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Completed
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
Completed
Radford Road near Gatwick Road, Crawley
Crawley
10 November 2025
14 November 2025
Completed
Sea Road near South Terrace, Littlehampton
Arun
24 November 2025
5 December 2025
Completed
-
November Update
Share November Update on Facebook Share November Update on Twitter Share November Update on Linkedin Email November Update linkWe have now completed 17 sites, with a further two sites scheduled for construction in November.
Junction refurbishment at Southgate has been completed a week early.
Please see below the November planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Completed
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
Currently under refurbishment
Radford Road near Gatwick Road, Crawley
Crawley
10 November 2025
14 November 2025
Sea Road near South Terrace, Littlehampton
Arun
24 November 2025
5 December 2025
We have now completed 17 sites, with a further two sites scheduled for construction in November.
Junction refurbishment at Southgate has been completed a week early.
Please see below the November planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Completed
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
Currently under refurbishment
Radford Road near Gatwick Road, Crawley
Crawley
10 November 2025
14 November 2025
Sea Road near South Terrace, Littlehampton
Arun
24 November 2025
5 December 2025
-
October Update
Share October Update on Facebook Share October Update on Twitter Share October Update on Linkedin Email October Update linkWe have now completed 15 sites, with a further two sites scheduled for construction in October.
Junction refurbishment at Southgate is progressing well. Meanwhile you can find FAQs and diversion route map for this project on left side of this webpage under the Documents section . Apologies for any inconvenience.
Please see below the October planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Currently under refurbishment
Chalcraft Lane nr Central Avenue, Bersted
Arun
6 October 2025
31 October 2025
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
We have now completed 15 sites, with a further two sites scheduled for construction in October.
Junction refurbishment at Southgate is progressing well. Meanwhile you can find FAQs and diversion route map for this project on left side of this webpage under the Documents section . Apologies for any inconvenience.
Please see below the October planned programme sites:
Location
District
Start date
Finish Date
Status
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Currently under refurbishment
Chalcraft Lane nr Central Avenue, Bersted
Arun
6 October 2025
31 October 2025
Felpham Way near Middleton Road, Felpham
Arun
27 October 2025
7 November 2025
-
September Update
Share September Update on Facebook Share September Update on Twitter Share September Update on Linkedin Email September Update linkWe have now completed 14 signalised crossings, with a further three sites scheduled for construction in September.
From Monday 22 September 2025, West Sussex County Council will be refurbishing the existing traffic signals junction of Stockbridge Road, Southgate & Basin Road, Chichester.
The A286 Stockbridge Road will be fully closed in both directions at the level crossing for approximately 8 weeks. A vehicle diversion route will be clearly signposted throughout this period.
Pedestrian access at level crossings and access to local businesses and train station carpark will be maintained at all times.
Meanwhile you can find FAQs and diversion route map for this project on left side of this webpage under the Documents section . Apologies for any inconvenience.
Please see below the September planned programme sites:
Location
District
Start date
Finish Date
Status
Brighton Road near Garage, Worthing
Adur & Worthing
1 September 2025
26 September 2025
Currently under refurbishments
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Main Road near Thorney Road, Chichester
Chichester
22 September 2025`
10 October 2025
We have now completed 14 signalised crossings, with a further three sites scheduled for construction in September.
From Monday 22 September 2025, West Sussex County Council will be refurbishing the existing traffic signals junction of Stockbridge Road, Southgate & Basin Road, Chichester.
The A286 Stockbridge Road will be fully closed in both directions at the level crossing for approximately 8 weeks. A vehicle diversion route will be clearly signposted throughout this period.
Pedestrian access at level crossings and access to local businesses and train station carpark will be maintained at all times.
Meanwhile you can find FAQs and diversion route map for this project on left side of this webpage under the Documents section . Apologies for any inconvenience.
Please see below the September planned programme sites:
Location
District
Start date
Finish Date
Status
Brighton Road near Garage, Worthing
Adur & Worthing
1 September 2025
26 September 2025
Currently under refurbishments
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester
Chichester
22 September 2025
7 November 2025
Main Road near Thorney Road, Chichester
Chichester
22 September 2025`
10 October 2025
-
August Update
Share August Update on Facebook Share August Update on Twitter Share August Update on Linkedin Email August Update linkWe have now completed 11 signalised crossings, with a further two sites scheduled for construction in August.
Please see below the August planned programme sites:
Location
District
Start date
Finish Date
Status
Barnham Road near Elm Grove, Barnham, Bognor Regis
Arun
23 July 2025
12 August 2025
Currently undergoing refurbishment
Westhampnett Road near Barnfield Drive, Chichester
Chichester
4 August 2025
22 August 2025
Currently undergoing refurbishment
Fransiscan Way near Duke Street, Littlehampton
Littlehampton
6 August 2025
29 August 2025
Currently undergoing refurbishment
From Monday 22 September 2025, West Sussex County Council will be refurbishing the existing traffic signals junction of Stockbridge Road, Southgate & Basin Road, Chichester.
The A286 Stockbridge Road will be fully closed in both directions at the level crossing for approximately 8 weeks. A vehicle diversion route will be clearly signposted throughout this period. Access to local businesses and train station carpark will be maintained at all times. We will be doing weekly updates for this project on this webpage. Meanwhile you can find FAQs for this project on left side of this webpage under the Documents section . Apologies for any inconvenience
We have now completed 11 signalised crossings, with a further two sites scheduled for construction in August.
Please see below the August planned programme sites:
Location
District
Start date
Finish Date
Status
Barnham Road near Elm Grove, Barnham, Bognor Regis
Arun
23 July 2025
12 August 2025
Currently undergoing refurbishment
Westhampnett Road near Barnfield Drive, Chichester
Chichester
4 August 2025
22 August 2025
Currently undergoing refurbishment
Fransiscan Way near Duke Street, Littlehampton
Littlehampton
6 August 2025
29 August 2025
Currently undergoing refurbishment
From Monday 22 September 2025, West Sussex County Council will be refurbishing the existing traffic signals junction of Stockbridge Road, Southgate & Basin Road, Chichester.
The A286 Stockbridge Road will be fully closed in both directions at the level crossing for approximately 8 weeks. A vehicle diversion route will be clearly signposted throughout this period. Access to local businesses and train station carpark will be maintained at all times. We will be doing weekly updates for this project on this webpage. Meanwhile you can find FAQs for this project on left side of this webpage under the Documents section . Apologies for any inconvenience
-
July Update
Share July Update on Facebook Share July Update on Twitter Share July Update on Linkedin Email July Update linkWe have now completed 10 signalised crossings, with a further two sites scheduled for construction in July.
Please see below the July planned programme sites:
Location
District
Start date
Finish Date
Status
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Complete
Grinstead Lane near Crabtree Lane, Lancing
Adur
23 June 2025
4 July 2025
Complete
Northgate Avenue near North Road, Crawley
Crawley
23 June 2025
11 July 2025
Currently undergoing refurbishment
Barnham Road near Elm Grove, Barnham, Bognor Regis
Arun
23 July 2025
12 August 2025
We have now completed 10 signalised crossings, with a further two sites scheduled for construction in July.
Please see below the July planned programme sites:
Location
District
Start date
Finish Date
Status
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Complete
Grinstead Lane near Crabtree Lane, Lancing
Adur
23 June 2025
4 July 2025
Complete
Northgate Avenue near North Road, Crawley
Crawley
23 June 2025
11 July 2025
Currently undergoing refurbishment
Barnham Road near Elm Grove, Barnham, Bognor Regis
Arun
23 July 2025
12 August 2025
-
June Update
Share June Update on Facebook Share June Update on Twitter Share June Update on Linkedin Email June Update linkWe have now completed 7 signalised crossings, with a further two sites scheduled for construction in June. Please see below the June planned programme sites:
Location
District
Start date
Finish Date
Status
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Currently undergoing refurbishment
Brighton Road near The Broadway, Lancing
Adur
19 May 2025
4 June 2025
Currently undergoing refurbishment
Grinstead Lane near Crabtree Lane, Lancing
Adur
23 June 2025
4 July 2025
Northgate Avenue near North Road, Crawley
Crawley
23 June 2025
11 July 2025
We have now completed 7 signalised crossings, with a further two sites scheduled for construction in June. Please see below the June planned programme sites:
Location
District
Start date
Finish Date
Status
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Currently undergoing refurbishment
Brighton Road near The Broadway, Lancing
Adur
19 May 2025
4 June 2025
Currently undergoing refurbishment
Grinstead Lane near Crabtree Lane, Lancing
Adur
23 June 2025
4 July 2025
Northgate Avenue near North Road, Crawley
Crawley
23 June 2025
11 July 2025
-
May Update
Share May Update on Facebook Share May Update on Twitter Share May Update on Linkedin Email May Update linkThe final year of the HRP programme is now fully underway. To date, five signalised crossing have been completed, with a further three sites scheduled for construction in May. One of the planned sites is the signalised junction at Terminus Road/Southern Gate/Leisure Centre access in Chichester, with work due to take place from 19 May to 4 July 2025. During this period, multi-way traffic management will be in place, potentially causing disruptions. These works are essential to convert the remaining bulbs to the new, more efficient technology.
Upgraded LED Signal heads and new tactile paving to assist visually impaired pedestrians on Worthing Road / Windmill Parade in LittlehamptonPlease see below the May 2025 Programme:
Location
District
Start Date
Finish Date
Status
Main Road near Canal Road, Yapton, Arundel
Arun
6 May 2025
16 May 2025
Currently undergoing refurbishment
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Brighton Road near The Broadway, Lancing
Adur
19 May 2025
4 June 2025
The final year of the HRP programme is now fully underway. To date, five signalised crossing have been completed, with a further three sites scheduled for construction in May. One of the planned sites is the signalised junction at Terminus Road/Southern Gate/Leisure Centre access in Chichester, with work due to take place from 19 May to 4 July 2025. During this period, multi-way traffic management will be in place, potentially causing disruptions. These works are essential to convert the remaining bulbs to the new, more efficient technology.
Upgraded LED Signal heads and new tactile paving to assist visually impaired pedestrians on Worthing Road / Windmill Parade in LittlehamptonPlease see below the May 2025 Programme:
Location
District
Start Date
Finish Date
Status
Main Road near Canal Road, Yapton, Arundel
Arun
6 May 2025
16 May 2025
Currently undergoing refurbishment
Terminus Road/Leisure Centre Access, Chichester
Chichester
19 May 2025
4 July 2025
Brighton Road near The Broadway, Lancing
Adur
19 May 2025
4 June 2025
-
April Update
Share April Update on Facebook Share April Update on Twitter Share April Update on Linkedin Email April Update linkThe traffic signal equipment previously deemed obsolete at Market Road near Eastergate Square in Chichester and Worthing Road, Littlehampton are now complete. The upgrade includes the installation of energy-efficient LED signal heads with straight poles that provide improved visibility for motorists.
Upgraded LED Signal heads on Market Road near Eastergate Square, ChichesterPlease see below the April programme sites:
Location
District
Start date
Finish Date
Status
Market Road near Eastgate Square and The Hornet near Eastgate Square, Chichester
Chichester
31 Mar 2025
04 Apr 2025
Complete
Worthing Road / Windmill Parade, Littlehampton
Arun
31 Mar 2025
11 Apr 2025
Complete
Northern Crescent near Windsort Drive, Chichester
Chichester
07 Apr 2025
17 Apr 2025
Complete
Terringes Avenue near Ringmer Road, Worthing
Adur & Worthing
22 Apr 2025
02 May 2025
Complete
The traffic signal equipment previously deemed obsolete at Market Road near Eastergate Square in Chichester and Worthing Road, Littlehampton are now complete. The upgrade includes the installation of energy-efficient LED signal heads with straight poles that provide improved visibility for motorists.
Upgraded LED Signal heads on Market Road near Eastergate Square, ChichesterPlease see below the April programme sites:
Location
District
Start date
Finish Date
Status
Market Road near Eastgate Square and The Hornet near Eastgate Square, Chichester
Chichester
31 Mar 2025
04 Apr 2025
Complete
Worthing Road / Windmill Parade, Littlehampton
Arun
31 Mar 2025
11 Apr 2025
Complete
Northern Crescent near Windsort Drive, Chichester
Chichester
07 Apr 2025
17 Apr 2025
Complete
Terringes Avenue near Ringmer Road, Worthing
Adur & Worthing
22 Apr 2025
02 May 2025
Complete
-
March Update
Share March Update on Facebook Share March Update on Twitter Share March Update on Linkedin Email March Update linkWest Sussex County Council will be refurbishing the existing traffic signals crossings on Market Road, near Eastgate Square/The Hornet, Chichester as part of the ongoing Halogen Replacement Programme. All obsolete equipment will be replaced with the latest technology including low energy LED signal heads.
The works will begin from Monday 31 March to Friday 4 April 2025 between 9:30 am - 3:30 pm. Two - way traffic management will be in place along with bus stop outside Turner's Pies will be suspended. Pedestrian access will be maintained at all times. Deliveries directly onto a property or driveway will not be affected. If the delivery is to be on street, then the driver will not be able to park in the barriered works area but will otherwise be able to deliver any portable packages direct to the property. Follow Causeway one.network .
As with all work on the Highway, it is subject to suitable weather; inclement weather may delay progress.
West Sussex County Council will be refurbishing the existing traffic signals crossings on Market Road, near Eastgate Square/The Hornet, Chichester as part of the ongoing Halogen Replacement Programme. All obsolete equipment will be replaced with the latest technology including low energy LED signal heads.
The works will begin from Monday 31 March to Friday 4 April 2025 between 9:30 am - 3:30 pm. Two - way traffic management will be in place along with bus stop outside Turner's Pies will be suspended. Pedestrian access will be maintained at all times. Deliveries directly onto a property or driveway will not be affected. If the delivery is to be on street, then the driver will not be able to park in the barriered works area but will otherwise be able to deliver any portable packages direct to the property. Follow Causeway one.network .
As with all work on the Highway, it is subject to suitable weather; inclement weather may delay progress.
Who's Listening
-
Cabinet Member for Highways and Transport
-
Asset Manager - Traffic Signals and Street Lighting
Important Links
Programme Update
-
Year 1 (23/24) Complete
Halogen Bulb Replacement Programme has finished this stageCompleted 3 junctions and 29 crossings.
-
Year 2 (24/25) Complete
Halogen Bulb Replacement Programme has finished this stageCompleted 2 junctions and 27 crossings
-
Year 3 (25/26) Under Refurbishment
Halogen Bulb Replacement Programme is currently at this stageApril 2025 to March 2026 - 3 junctions and 24 crossings
FAQs
- Why is West Sussex County Council doing this?
- What is WSCC changing?
- How will this impact on climate?
- How much will the project cost?
- How will the project be funded?
- Why are the traffic signals in West Sussex only recently being changed to LED?
- What does a LED traffic signal look like?
- Will you be digging up the road?
- How long will the new LED bulbs last?
- How do you know LED is reliable now?
- What is the Remote Monitoring System and how will it help?
- Is it true that the LED lights are too bright according to reports?
- When will my area have LED traffic signals fitted?