December Update
We have now completed 19 sites, with a further one site is now completed. The Halogen Replacement Programme will now resume in January 2026.
Please see below the November planned programme sites:
Location |
District |
Start date |
Finish Date |
Status |
Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester |
Chichester |
22 September 2025 |
7 November 2025 |
Completed |
Felpham Way near Middleton Road, Felpham |
Arun |
27 October 2025 |
7 November 2025 |
Completed |
Radford Road near Gatwick Road, Crawley |
Crawley |
10 November 2025 |
14 November 2025 |
Completed |
Sea Road near South Terrace, Littlehampton |
Arun |
24 November 2025 |
5 December 2025 |
Completed |