December Update

We have now completed 19 sites, with a further one site is now completed. The Halogen Replacement Programme will now resume in January 2026.

Please see below the November planned programme sites:

Location

District

Start date

Finish Date

Status

Southgate Road, Junction of Southgate Link near Chichester Bus Station, Chichester

Chichester

22 September 2025

7 November 2025

Completed

Felpham Way near Middleton Road, Felpham

Arun

27 October 2025

7 November 2025

Completed

Radford Road near Gatwick Road, Crawley

Crawley

10 November 2025

14 November 2025

Completed

Sea Road near South Terrace, Littlehampton

Arun

24 November 2025

5 December 2025

Completed