June Update
We have now completed 7 signalised crossings, with a further two sites scheduled for construction in June. Please see below the June planned programme sites:
Location |
District |
Start date |
Finish Date |
Status |
Terminus Road/Leisure Centre Access, Chichester |
Chichester |
19 May 2025 |
4 July 2025 |
Currently undergoing refurbishment |
Brighton Road near The Broadway, Lancing |
Adur |
19 May 2025 |
4 June 2025 |
Currently undergoing refurbishment |
Grinstead Lane near Crabtree Lane, Lancing |
Adur |
23 June 2025 |
4 July 2025 |
|
Northgate Avenue near North Road, Crawley |
Crawley |
23 June 2025 |
11 July 2025 |
|