July Update

We have now completed 10 signalised crossings, with a further two sites scheduled for construction in July.

Please see below the July planned programme sites:


Location

District

Start date

Finish Date

Status

Terminus Road/Leisure Centre Access, Chichester

Chichester

19 May 2025

4 July 2025

Complete

Grinstead Lane near Crabtree Lane, Lancing

Adur

23 June 2025

4 July 2025

Complete

Northgate Avenue near North Road, Crawley

Crawley

23 June 2025

11 July 2025

Currently undergoing refurbishment

Barnham Road near Elm Grove, Barnham, Bognor Regis

Arun

23 July 2025

12 August 2025