12 May 2025

Works start on Middle Road improvements

Works will commence from 12th May for approx. 2 weeks to upgrade the existing 2 build outs and provide a cycle bypass.

26 May 2025

Upper Shoreham Road ducting works for New Speed Camera Location commences

Upper Shoreham Road  by junction Buckingham Close– The ducting and connection works for the speed camera will start 26th May for approximately 3 weeks under temporary traffic signals

27 October 2025

Buckingham Road resurfacing of carriageway works commences

Buckingham Road carriageway resurfacing – Works are now being programmed for 27th-31st October for half term as the road will be closed for safety and to minimise disruption to the school.

22 July 2025

Buckingham Road School Gate improvements commence

Buckingham Road – Works will continue on the installation of the shared cycleway until 16th May. Works will be paused o/s no. 64 until the School summer holidays to ensure minimal disruption.