Week 4 Update

Week 4 Summary

The contractors' main focus this week has been within section 3 (please see drawings under photos sections on right side of the webpage):

  • Reduced level excavation for the new bus lane.
  • Working with Southern Gas Network (SGN) to dig a trench for the gas main diversion route.
  • Installing Heras fencing around trees within working area to provide tree protection in line with West Sussex tree arboriculturist's guidelines.

Look Ahead – Week 5 (Section 3)

  • Traffic Management Implementation: A designated running lane will remain in place to allow construction plant and dumpers to operate within the working area, reducing the need for vehicular movements on verges.
  • Gas Main Diversion Works: Trenching activities will continue in collaboration with SGN to facilitate the diversion of existing gas infrastructure.
  • Bus Lane Excavation: Earthworks will continue for the new bus lane within Section 3.
  • Pedestrian Access: The pedestrian crossing within Section 3 will remain closed however, alternative crossing points to the East and West will remain fully operational.

We remain committed to ensuring minimal disruption and maintaining safety standards throughout the duration of the project. Thank you for your continued support.