September 2023 → July 2024

School Streets Phase 1 Delivery and Trial

The school street trial was successfully run during the 23/24 school year.  Engagement and report details can be found in the documents section.

09 August 2024

Phase 1 Delivery - School Streets Reports Published

Both reports from WSCC School Streets Team and our partners Sustrans are now available to view in the documents section.

03 September 2024

School Streets Phase 2 Delivery commences

School Streets scheme investigation, monitoring and engagement for 24/25 school year commence for 

St Josephs Infant and Junior Schools, Orchard Gardens, Chichester.

River Beach Primary School, Connaught Road (access) Littlehampton.

The Mill Primary Academy, Shipley Road, leading to Southwater Close (access), Crawley.

06 January 2025

School Street Phase 2 Delivery In School Education commences

In school education commences at School Streets schools through Sustrans and Living Streets.

22 April 2025

School Streets Phase 2 Go Live

Following delivery of infrastructure, education and engagement the school street restriction goes live (projected date, could be subject to change)

27 July 2026

School Streets Phase 1 - Highway Improvements Delivery

Delivery of highway improvements at

Swiss Gardens Primary School, Shoreham

Thomas a Becket Junior School, Worthing

Arundel Primary School, Arundel