What has the scheme delivered?

    The scheme has upgraded the Esplanade between Lennox Street and Clarence Road. This included improved pedestrian and disabled access between the Esplanade and seafront, decreased the speed limit to improve safety, increased planting and installation of additional seating and litter bins.

    Who delivered the Esplanade scheme?

    These works were delivered by WSCC, in partnership with ADC as part of the wider Arun Growth Programme. WSP continue to provide project management support.

    On 6th September 2024, a Key Decision (opens in a new tab) was published appointing Landbuild Ltd as the contractor for these works. 

    How was the scheme funded?

    The Esplanade Scheme budget was £1.8 million in total. The scheme was funded by the Arun Growth Programme which is a partnership programme with West Sussex County Council (WSCC) and Arun District Council (ADC).

    When did the works on the Esplanade take place?

    Works commenced on the Esplanade on 4th November and completed in early April 2025.

    How does this scheme fit in with wider plans for the town?

    The Bognor Regis Esplanade Public Realm Improvements are one of six infrastructure projects taking place to improve the look and feel of Bognor Regis seafront. In August 2022, the Place St Maur Open Space was the first of the set of improvements to be completed and in April 2025, the Esplanade also completed. The Alexandra Theatre, Regis Centre (former Brewers Fayre building), Bognor Regis Arcade and the Premier Inn development are all planned for construction in the next few years.

Project Features

    Was there an increase/decrease in parking and cycle spaces?

    Overall, there was a net reduction of 19 parking spaces in order to establish improved pedestrian safety.  ADC are in the process of reviewing utilisation of their off street car parks across the town, with early indications that the net loss in parking along the Esplanade can be managed by off street parking availability.

    The scheme did not include the provision of additional cycle parking, at this time, but this could be added on land adjacent to the scheme in the recently completed Place St Maur area with the agreement of the District Council.  


    Was a cycle link to the town centre installed?

    The WSCC project team discussed the potential for a new cycle link between the Promenade, the Esplanade (at the central crossing) and across Place St Maur, crossing Belmont Street and using York Road. However, the costs of major changes to the sea wall and upgrade of the current Puffin Crossing to a Toucan Crossing, and difficulties establishing a route through the recently upgraded Place St Maur resulted in a cycle link being ruled out at this time.

    Was there an increase/decrease in trees?

    There was an addition of new trees alongside those that are currently there, where underground utilities, drainage and clearance to traffic signals could be maintained.

    Will there be a seasonal closure of the Esplanade?

    Discussions have been held between the Highway Authority and the District Council on the potential to allow for a seasonal closure of the Esplanade between April and October each year.  Although this might be seen as a benefit, the removal of car parking along this section, which provided around 22,000 parking events in the same period in 2021, and for which there would not be a re-provision of parking elsewhere, would likely remove significant footfall from the area and have a direct impact on the immediate local businesses on the seafront.  If temporary closures of the Esplanade, for specific events, is required there are sufficient existing powers that the District Council can use.

    A traffic report prepared by ADC and their consultant, WSP, of the potential highway impacts of a closure has also been completed and, in the medium to long term, traffic growth in the area would require some junction improvement, for which there is no currently identified funding, or a substantive increase in active travel modes such as walking and cycling to reduce car use.

Impacts of the Scheme

    What are the positive impacts of the scheme?

    Benefits of the scheme include:

    • Improved place shaping
    • Improved pedestrian access and disabled access between the Esplanade and Seafront, additional crossing facility to the west of the scheme with raised table crossing
    • The addition of a walkway between parked cars and sea wall to improve pedestrian safety
    • Creation of a 20mph zone through traffic calming features, road narrowing and removal of centreline markings to change the ‘character’ of the road and assist in making it more pedestrian friendly
    • Greening of the area with planting to create pleasant surroundings
    • Additional seating areas and provision of litter bins
    • Assist in urban regeneration around the Regis centre to help attract visitors to the sea front and improve economic growth.

    Are there any negative impacts of the scheme?

    The Esplanade Scheme is predominantly a highway and public realm improvement and seeks to improve accessibility, safety and to “green” the area at key crossing locations and along the road.  It is not believed that this will have any negative effects on customers, businesses or residents.

    How will the scheme reduce discrimination, harassment and victimisation?

    Improved footway access to the seafront; provision of the sea wall walkways and additional seating and waiting areas should have a positive effect on a variety of groups of people.

    Will there be any environmental impact, including air pollution?

    We are aware that during works like this traffic delays can take place, and this has an impact on the environment over the scheme delivery period. However, this scheme aims to improve environmental conditions for the town by promoting walking and cycling to encourage the shift to more sustainable modes of transport. 

    Additionally, the scheme has introduced new plants to the area.